Warehouse Racking for FDI Companies in Vietnam: Documents, Process & Checklist

Warehouse racking for FDI companies in Vietnam – especially Japanese and Korean factories – involves very different requirements from an ordinary racking order: a complete technical documentation package, drawing approval before fabrication, clear load signs, milestone-based scheduling and strict compliance with in-house safety rules. Drawing on experience since 1997 – nearly 30 years – of working with FDI plants in industrial parks across northern Vietnam, Long Quyen has summarized what FDI companies typically need when investing in a warehouse racking system.

How does racking procurement at an FDI company differ from a local company?

Buying racking for an FDI plant is much like buying equipment for a production line: the buyer receives not just “steel” but a full set of supporting documents proving that the equipment is safe, built to specification and backed by a supplier who takes long-term responsibility. The main differences are:

  • Multi-level approval: the warehouse team, EHS (environment, health & safety), maintenance, purchasing and sometimes the parent company in Japan, Korea or elsewhere.
  • Bilingual documentation: quotations, drawings and technical descriptions are usually required in English, and sometimes in Japanese or Korean.
  • Safety and durability ahead of the lowest price: suppliers are selected on technical capability, experience with similar projects and after-sales service.
  • Schedules tied to the production plan: racking typically has to be installed before machinery arrives or before the first inbound shipment of raw materials.
Forklift aisle between two rows of selective pallet racking in the raw-material warehouse of an FDI factory installed by Long Quyen
Selective pallet racking in the raw-material warehouse of an FDI factory, installed by Long Quyen.

Technical documents typically required

Document Purpose
Racking layout plan Approval of forklift aisles, emergency exits and fire-protection equipment locations
Detailed elevation and section drawings Checking beam level heights, clearances and sprinkler/lighting heights
Structural load calculation report Demonstrating level load, frame load, beam deflection and floor loading
Material certificates (steel CO/CQ) Traceability of steel origin and quality
Coating procedure and paint film thickness Meeting corrosion-protection and warehouse-environment requirements
Installation method statement and work-safety plan Approved by EHS before the crew enters the plant
Acceptance records, load signs and user manual Handover and operation in line with the design

Learn how these load parameters are calculated in our article on how to calculate pallet racking load capacity.

Close-up of the upright frame, beams and bracing of powder-coated pallet racking – the basis for drawings and load calculations for an FDI factory
Upright frame, beam and bracing details – the parameters shown in the drawings and load calculation report.

Six-step process for an FDI factory racking project

  1. Site survey: measure the floor area, clear height, and positions of columns, beams, sprinklers and floor expansion joints; confirm pallet type, loads and forklifts in use.
  2. Proposal: usually 2–3 options (e.g. Selective, Double Deep, Drive-in) with pallet positions and pros and cons for the owner to compare.
  3. Design freeze and documentation: finalize drawings, technical description and bill of quantities for internal approval.
  4. Fabrication: processing, powder coating and quality inspection before dispatch.
  5. Installation: the installation crew follows plant rules (personnel registration, PPE, work-at-height permits).
  6. Acceptance and handover: load signs installed, as-built documents, user manual and periodic inspection plan handed over.

See also Long Quyen’s warehouse design service.

Completed warehouse racking system at an FDI factory, ready for acceptance and handover according to the approved drawings
Completed racking system, ready for acceptance and handover with load signs and user manual.

Racking types commonly used in FDI factories

  • Selective pallet racking – raw-material and finished-goods warehouses with many SKUs that need 100% access to every pallet.
  • Medium-duty shelving – components, spare parts and tools for the maintenance department.
  • Carton flow racking – FIFO parts supply to assembly lines, well suited to Lean/Kaizen practices.
  • Mold and die racking – storage of heavy injection molds and stamping dies in plastics and metalworking plants.
  • Mezzanine floors – extra storage or warehouse office space without new construction.
Carton flow racking supplying components to an assembly line on a FIFO basis at an FDI factory
Carton flow racking supplying components to the assembly line on a FIFO basis.

Checklist for purchasing teams when selecting a racking supplier

  • Does the supplier have its own factory, or is it only a trader?
  • Has it completed projects for FDI plants in the same industry? Can you visit a real installation?
  • Will it provide a load calculation report and drawings before the contract is signed?
  • What are the warranty period, maintenance policy and response time when issues occur?
  • Does it have its own installation crew that can meet the plant’s EHS requirements?

Besides the racking itself, many plants also fit pallet racking safety accessories from day one to pass EHS inspections.

Frequently asked questions

Does Long Quyen provide documents in English, Japanese and Korean?

Yes. Long Quyen offers product information in English, Japanese and Korean, and supports bilingual quotations and drawings as each project requires.

How long does a factory warehouse racking project usually take?

It depends on the scale and on how long the owner’s document approval takes. Small and medium projects usually take a few weeks from design freeze; large projects are split into milestones to match the plant’s delivery schedule.

Which areas does Long Quyen serve?

Long Quyen is headquartered in Hanoi and installs nationwide, regularly working in industrial parks in Hanoi, Bac Ninh, Hung Yen, Hai Duong, Hai Phong, Vinh Phuc and Thai Nguyen. Call +84 903 422 179 (Zalo) for a free site survey.